Civil action commenced in the Superior
Court Department on July 20, 2018.
Motions for summary judgment were heard by
Diane C. Freniere, J., and the case was heard by Camille F. Sarrouf, Jr., J.
Scott P. Fink for the plaintiff.
Robert M. Shaw (Benjamin M. McGovern also
present) for the defendants.
DITKOFF, J. In this commercial lease contract dispute,
the parties cross-appeal from a judgment after a partial summary judgment order
and a bench trial in the Superior Court.
We conclude that the partial summary judgment order interpreting the
twice-amended contract was proper.
Further concluding that the contract provision providing for actual
damages "plus $500 per each day" for certain late work constitutes an
unenforceable penalty and that the actual damages awarded were proven with
reasonable certainty, we affirm.
Pursuant to the parties' contract providing attorney's fees to the
"prevailing party" to any lawsuit, we award each party appellate
attorney's fees for work expended in defending the Superior Court judgment,
either as appellee or cross appellee.
1.
Background. In 2013, a developer,
FMP Realty Trust, and a franchisor entered into a commercial lease for a
property in Tyngsboro, Massachusetts.
The lease required the developer to build a child care center and obtain
a certificate of occupancy within 180 days of receiving a building permit. The developer missed the deadline by almost
two years.
In 2016, the developer and the franchisor
signed an amendment to the lease (first amendment), which set a new deadline
for a temporary certificate of occupancy and increased the rent. The first amendment would be "null [and]
void" if the deadline was not met. The
town building inspector verbally authorized the franchisor to move in furniture
and furnishings by the deadline, but the certificate of occupancy issued
thirty-five days late.
Once the building was occupiable, the
developer assigned its rights and obligations to the landlord, MDC Properties
-Westford Rd, LLC, and the franchisor assigned its rights and obligations to
the tenant, Mittas Early Learning, LLC.
In October 2016, pursuant to the lease, the tenant provided the landlord
with written notice of unfinished work (punch list), which included heating,
ventilation, and air conditioning (HVAC) maintenance issues, for the landlord
to complete. The lease entitled the
tenant to actual damages plus $500 per day punch list items remained
uncompleted after thirty days.
In 2017, the parties executed a second
amendment to the lease. The second
amendment stated, "Except as expressly amended herein, all the terms and
conditions of the Lease as amended shall remain in full force and effect and
are hereby ratified and confirmed by the parties hereto." The second amendment required the landlord to
repair and maintain the HVAC system.
Nonetheless, the HVAC system remained inadequate until February 2020.[2]
The tenant sued the landlord and the
developer. A motion judge granted
partial summary judgment to the defendants, holding that the first and second
amendments were enforceable. After a
bench trial, the trial judge found that the defendants committed a breach of
the lease, as amended, and committed a breach of the implied covenant of quiet
enjoyment by failing to resolve the HVAC issues and awarded the tenant $25,000
in actual damages, but not an extra $500 per day.[3] Both sides appealed.
2.
Partial summary judgment. a. Standard of review. "We review a grant of summary judgment
de novo to determine 'whether, viewing the evidence in the light most favorable
to the nonmoving party, all material facts have been established and the moving
party is entitled to judgment as a matter of law.'" Cottrell v. Laidley, 103 Mass. App. Ct. 483,
489 (2023), quoting Chambers v. RDI Logistics, Inc., 476 Mass. 95, 99
(2016). We start by interpreting the
contract. "The words of a contract
must be considered in the context of the entire contract rather than in
isolation," and "[w]hen the words of a contract are clear, they must
be construed in their usual and ordinary sense." Brigade Leveraged Capital Structures Fund
Ltd. v. PIMCO Income Strategy Fund, 466 Mass. 368, 373-374 (2013), quoting
General Convention of the New Jerusalem in the U.S. of Am., Inc. v. MacKenzie,
449 Mass. 832, 835 (2007). Similarly,
"every word is to be given force so far as practicable," Beninati v.
Borghi, 90 Mass. App. Ct. 556, 563 (2016), quoting MacDonald v. Hawker, 11
Mass. App. Ct. 869, 872-873 (1981), to avoid rendering any "part useless
or inexplicable." First Specialty
Ins. Corp. v. Pilgrim Ins. Co., 83 Mass. App. Ct. 812, 819 (2013), quoting
Worcester Mut. Ins. Co. v. Marnell, 398 Mass. 240, 245 (1986).
b.
Operability of the amendments.
The tenant argues that the first amendment is not operable because,
under the terms of the first amendment, if the developer missed certain
deadlines, the "Amendment shall immediately be deemed null, void, and of
no further force or effect." The
tenant alleges that the first amendment was breached when the landlord failed
to "obtain at least a [temporary certificate of occupancy] on or before
August 10, 2016." The tenant argues
that, without the first amendment, it is entitled to over twenty-one months of
free rent, one day of free rent for each day that the developer missed the
original certificate of occupancy due date.
We need not decide whether the first amendment would be void under its
own terms because the second amendment revived the first amendment.
Under the second amendment, "[e]xcept
as expressly amended herein, all the terms and conditions of the Lease as
amended shall remain in full force and effect and are hereby ratified and
confirmed by the parties hereto."
This language was adopted by the parties after the deadline in the first
amendment, so by its plain language, if the first amendment had become void,
this provision revived it. This revival
is further evinced by the prorated rent agreed to in the second amendment. The parties agreed to the pro rata amount of
$3,215.72 for January rent starting January 3, 2017. This amount matches the higher amount due
under the table in the first amendment, not the lower amount that would have
been due under the unamended lease.
Because the second amendment revived the first amendment, the rent
tables in the first amendment are operable.
Another provision of the second amendment
"waive[d], disclaim[ed], and release[d] any claim for default or breach of
the Lease," contingent upon "performance of any and all obligations
required" under the second amendment.
The tenant argues that, under this provision, because the landlord
breached the second amendment to the lease, the second amendment no longer
revives the first amendment. This
argument conflates different provisions of the second amendment. Although it is certainly true that, when the
landlord breached the second amendment to the lease, the waiver of claims for
breach of the lease failed, this provision does not impact the separate
provision confirming that the lease remains amended by both the first and
second amendments.
3. Damages. a.
Standard of review. In reviewing
a judgment entered after a jury-waived trial, we set aside the trial judge's
findings of fact only if clearly erroneous.
Goddard v. Goucher, 89 Mass. App. Ct. 41, 44 (2016). The trial judge's legal conclusions, however,
are reviewed de novo. Id.
b.
Liquidated damages. A contractual
provision that provides for a penalty for a breach of contract is
unenforceable. See Nantasket Beachfront
Condominiums, LLC v. Hull Redev. Auth., 87 Mass. App. Ct. 455, 469 (2015). A proper liquidated damages provision,
however, is not a penalty.
"'Liquidated damages' is a term derived from contract law to
identify the amount of damages that the parties agree must be paid in the event
of a breach." George v. National
Water Main Cleaning Co., 477 Mass. 371, 375 (2017). "When parties agree in advance to a sum
certain that represents a reasonable estimate of potential damages, they
exchange the opportunity to determine actual damages after a breach, including
possible mitigation, for the 'peace of mind and certainty of result' afforded
by a liquidated damages clause."
NPS, LLC v. Minihane, 451 Mass. 417, 423 (2008), quoting Kelly v. Marx,
428 Mass. 877, 881 (1999).
"A contractual liquidated damages
provision is entitled to a presumption of validity, especially where
. . . it was negotiated between two sophisticated parties." Cummings Props., LLC v. Hines, 492 Mass. 867,
873 (2023), quoting Nantasket Beachfront Condominiums, LLC, 87 Mass. App. Ct.
at 469. It "will usually be
enforced, provided two criteria are satisfied:
first, that at the time of contracting the actual damages flowing from a
breach were difficult to ascertain; and second, that the sum agreed on as
liquidated damages represents a 'reasonable forecast of damages expected to
occur in the event of a breach.'"
George, 477 Mass. at 375, quoting NPS, LLC, 451 Mass. at 420. "The burden of showing that a liquidated
damages provision is unenforceable rests with the party challenging enforcement
of the provision." NPS, LLC,
supra. "Whether a liquidated
damages provision in a contract is an unenforceable penalty is a question of
law." Id. at 419.
Under the lease, if the punch list items
were not completed on time, the "Landlord shall pay Tenant the sum of its
actual damages plus $500 per each day until completion of all items." This is not actually a liquidated damages
clause at all. By adding $500 per day to
the actual damages, the clause definitionally guarantees that the damages
calculated under the clause will be greater, likely vastly greater, than the
actual damages. See SMS Fin. V, LLC v.
Conti, 68 Mass. App. Ct. 738, 751 (2007) ("Where liquidated damages are
greatly disproportionate to actual damages arising from a breach, the
liquidated damages are deemed a penalty and are not enforced"). Rather than "exchange the opportunity to
determine actual damages after a breach, including possible mitigation, for the
'peace of mind and certainty of result' afforded by a liquidated damages
clause," NPS, LLC, 451 Mass. at 423, quoting Kelly, 428 Mass. at 881, this
clause simply adds a penalty to the calculation of actual damages. The trial judge properly discerned that this
clause constituted an unenforceable penalty and properly imposed damages for
the actual damages suffered by the tenant.
c.
Actual damages. "The
plaintiff has the burden of proving [its] damages 'with reasonable
certainty.'" Coady v. Wellfleet
Marine Corp., 62 Mass. App. Ct. 237, 245 (2004), quoting Agoos Leather Cos. v.
American & Foreign Ins. Co., 342 Mass. 603, 608 (1961). Nonetheless, "the amount of damages need
not be proved with mathematical precision; the extent of damages often must be
left to estimate and judgment."
Bleicken v. Stark, 61 Mass. App. Ct. 619, 624 (2004), quoting Our Lady
of the Sea Corp. v. Borges, 40 Mass. App. Ct. 484, 488 (1996). "The sole issue before us in deciding
whether to uphold the [fact finder]'s damage award is whether [the plaintiff]
presented sufficient evidence to permit the [fact finder] to find that the
amount of . . . damages had been proven to a reasonably approximate
certainty." Brewster Wallcovering
Co. v. Blue Mountain Wallcoverings, Inc., 68 Mass. App. Ct. 582, 611 n.65
(2007).
Here, the tenant proved its damages with
reasonable certainty. The proprietor of
the tenant testified that the HVAC system problems increased utility costs and
required staff to monitor the contractors.
Regarding utility costs, the proprietor testified that he compared how
much he spent on this facility versus other facilities that he operates, which
have similar (but fully functioning) HVAC systems. He estimated that, over the period of four
years, he spent $5,000 more on this facility in utility costs. Regarding staff costs, he went "through
the log of contractor visits that were made in the last three to four years,
and [he had] estimated how much -- how many payroll hours [his] staff would
have spent, whether [they're] exempt or not exempt. And based on [his] average pay rate, based on
what [his] payroll is, [he could] come up with some estimate." That estimate was $20,000. Although the proprietor couched his estimates
using phrases like, "I think it might be $20,000," this "element
of uncertainty as to the amount of damages does not bar their
recovery." Coady, 62 Mass. App. Ct.
at 245, quoting Stuart v. Brookline, 412 Mass. 251, 256-257 (1992). In any event, this imprecision was consistent
with the way the proprietor delivered his other testimony at trial, and the
judge, sitting as fact finder, could reasonably conclude that the proprietor's
use of qualifiers was part of his speaking style as opposed to expressing
speculation.
4.
Appellate attorney's fees. Under
the lease, "[i]f any action or lawsuit is brought to enforce any of the
provisions of this Lease, the prevailing party to any such lawsuit shall be
entitled to reimbursement of all reasonable costs and expenses, including
reasonable attorney's fees from the non-prevailing party at pre-trial, trial
and all appellate levels." All
parties request attorney's fees and costs on appeal.
Confusion arises here because both sides
are prevailing parties on the appeal, one as appellee and one as cross
appellee. The United States Court of
Appeals for the Eighth Circuit faced such a situation in Newhouse v. McCormick
& Co., 130 F.3d 302, 303-305 (8th Cir. 1997), in which the court concluded
that the appellee was entitled to attorney's fees for prevailing on a
discrimination claim, and the cross appellee was entitled to attorney's fees
for prevailing against a frivolous cross appeal. The court awarded attorney's fees to each
party for the work done as appellee or cross appellee. See id. at 304-305.[4] We have previously suggested that the same
approach would apply in Massachusetts.
See Brady v. Citizens Union Sav. Bank, 91 Mass. App. Ct. 160, 164 &
n.10 (2017) (stating that both parties may be considered prevailing parties on
appeal, but awarding fees only to party requesting them).
We adopt the approach of the Eighth
Circuit and award each side its appellate attorney's fees where it prevailed in
the current lawsuit, which is this appeal.
Here, each party prevailed in its role as appellee or cross appellee in
defending the Superior Court judgment.
Specifically, the defendants are entitled to fees for the first three
parts of their principal and response brief, see Mass. R. A. P.
19 (b) (2), as appearing in 481 Mass. 1642 (2019), which defended the
Superior Court's judgment. They are not
entitled to fees for the fourth part of that brief, which unsuccessfully asked
us to reverse the award of $25,000 in damages to the tenant, or for their reply
brief, see Mass. R. A. P. 19 (b) (4), which argued the
same. Similarly, the tenant is entitled
to fees for the third part of its response and reply brief, see Mass.
R. A. P. 19 (b) (3), which defended the $25,000 in actual
damages. It is not entitled to fees for
its principal brief, see Mass. R. A. P. 19 (b) (1), or for
the first and second parts of its response and reply brief, which argued for
reversing the judgment and awarding additional damages.
We are cognizant that this will pose
practical difficulties in determining what fees are proper for other
expenditures that are not so easily separated, such as oral argument
preparation time. Each party seeking attorney's
fees, however, bears the burden of establishing that the amount requested is
reasonable in light of the issues on which it prevailed, see Beninati, 90 Mass.
App. Ct. at 568; Wodinsky v. Kettenbach, 86 Mass. App. Ct. 825, 839 (2015), and
will not recover fees where it is unable to meet that burden. See Newhouse, 130 F.3d at 304 (reducing award
by approximately one-third because, among other reasons, "work done on his
unsuccessful cross-appeal should not be compensated by Newhouse's
opponent"); id. at 305 ("[E]ven though McCormick was the appellant in
the main appeal and its counsel would have had to travel to St. Paul in
any event to argue its own appeal, it seeks to charge all of its counsel's
travel time, his preargument preparation time, his oral argument time, and his
travel and lodging expenses to and in St. Paul to Newhouse. That we cannot abide").[5]
Judgment
affirmed.
footnotes
[1] Frank M.
Polak, trustee of the FMP Realty Trust.
[2] At $500 per
day, starting thirty days after the punch list was provided, the lease required
a payment of actual damages plus approximately $600,000 for the landlord's
failure to remedy the HVAC problems sooner.
[3] The judge
also found that the defendants had not violated the implied covenant of good
faith and fair dealing. The plaintiff
does not challenge this finding on appeal.
[4] This may not
be the right approach in other circumstances.
See, e.g., Royal Palm Props., LLC v. Pink Palm Props., LLC, 38 F.4th
1372, 1378 (11th Cir. 2022) (holding that Fed. R. Civ. P. 54, concerning costs
at trial level, does not allow for multiple prevailing parties); Domain
Protection, L.L.C. v. Sea Wasp, L.L.C., 23 F.4th 529, 540 (5th Cir. 2022)
("When both sides achieve some litigation victories on a claim, there may
not be a prevailing party").
[5] Consistent
with the procedure set out in Fabre v. Walton, 441 Mass. 9, 10-11 (2004), each
party may submit an application for the part of its appellate attorney's fees
and costs attributable to its role as appellee or cross appellee, with
supporting documentation, to this court within fourteen days of the date of
this opinion. Each party shall have
fourteen days thereafter to respond to the other side's application.